Update of work on Spruce Creek Bridge project
July 31, 2025 – Northland Constructors has both the north and south abutments and wingwalls poured. Falsework building for the concrete deck has begun as well. The deck should be poured on Wednesday or Thursday of next week and from there, approach work and road work will continue. With the recent rains, progress slowed down due to very high water in the creek.